Project News Details
Title:
U.S. Solar developer seeks connection to wrong powerline, delays project five years
Detail:
The OFW Solar Project in Virginia submitted an application to connect to powerlines run by the wrong power company, instead of a second set of nearby transmission lines, necessitating a total restart of the PJM interconnection process that could push construction back to 2032.
Source:
PV-Magazine
Published Date:
12.05.2026