Taichung Power Plant Project Construction Underway with Unit 1 First Fire Achieved
Detail:
Taiwan Power Company is constructing two gas-fired Combined Cycle units totaling 2.6 GW adjacent to the existing Taichung coal plant, including Taiwan's first self-operated LNG terminal with five storage tanks. Power block bid awarded in 2020, first fire for Unit 1 on 2025-06-30, with installation and testing ongoing; Unit 1 COD scheduled for 2025-08-31 and Unit 2 for 2026-08-31.